Information for neighbours

We know your neighbourhood is important to you. The redevelopment at Carlton will mean more modern, secure and sustainable homes for Victorians that need it the most. 

It will also mean better pathways and connections, and public spaces for the whole community. 

Crane installation

To bring the 2 red brick buildings down safely and efficiently, we will install a tower crane in August, and this will remain in place during the deconstruction works.  

To safely install the tower crane, a smaller mobile crane will be brought on site for 3 days. 

Temporary traffic changes will be in place on Elgin Street, between Canning and Nicholson Street, during these 3 days.  

Works and traffic changes will include: 

  • Removal of car parks in front of the work site (Friday 8 August to Sunday 10 August). 
  • Footpath closure in front of the work site (Saturday 9 August and Sunday 10 August). 
  • Closure of Elgin Street, between Canning and Nicholson Street (Sunday 10 August). 
  • Relocation of the Elgin Street bus stop towards Canning Street (Friday 8 August and Saturday 9 August). 
  • Closure of the Elgin Street bus stop (Sunday 10 August).  

Traffic controllers will be located at the site entrance, to allow safe movement of machinery and works. Please follow all safety signage.  

These works will be carried out in compliance with the City of Melbourne’s Local Laws and Code of Practice for Building and Construction Works.

We recommend you allow extra time to reach your destination on time during these works.  

When will this tower crane work take place? 

  • Friday 8 August, 6:00 am – 6:00 pm 
  • Saturday 9 August, 6:00 am – 6:00 pm 
  • Sunday 10 August, 6:00 am – 6:00 pm  

These dates may change due to unforeseen circumstances such as weather. We will keep the community informed. 

You can view the detailed traffic management plans at the end of this page.  

City of Melbourne stipulate a 14-day consultation period for these works. You can find our contact details below and our team will be happy to answer any questions. 

Current and upcoming works

Traffic changes on Palmerston Street 

Work site establishment  

What to expect during deconstruction

What can I expect?

What times will works occur?

How will I be notified about upcoming works?

Will there be noise, dust and vibration?

Will there be any contaminated building materials such as asbestos?

Will there be a crane on site?

Still have questions?

For more information about this project, please send us an email or call John Holland project hotline